Improvement Project
Data project dibaca dari spreadsheet Project Control, yang tetap menjadi sumber kebenaran.
45 project
| Kode | Nama project | Departemen | PIC | Selesai (rencana) | Progress | Selisih | Status |
|---|---|---|---|---|---|---|---|
| MOP-01 | 5R Implementation P1 People & Culture | QAQC | — | 09 Nov 2026 | 29,7% | -70,3% | Delayed |
| MOP-02 | Bentuk CI + OBEYA P1 People & Culture | COO + CI | — | 06 Nov 2026 | 51,5% | -48,5% | Delayed |
| MOP-03 | SOP Project (collab HC) P1 People & Culture | QAQC | — | 31 Des 2026 | 29% | -21% | At Risk |
| MOP-04 | COGM Project P2 Cost & Productivity | Operations (COO) | — | 23 Nov 2026 | 60% | -28% | Delayed |
| MOP-05 | Kurasi Pareto C by Manuf P2 Cost & Productivity | R&D | — | 30 Nov 2026 | 0% | -77,2% | Delayed |
| MOP-06 | MC Development & Balancing P2 Cost & Productivity | Engineering | — | 26 Feb 2027 | 5% | -25,3% | Delayed |
| MOP-07 | ERP v.1 – SPK Fully Operate P3 Digital & Data | PPIC | — | 31 Des 2026 | 100% | +50% | Completed |
| MOP-08 | Automate ERP B2B – COGM P3 Digital & Data | Operations (COO) | — | 28 Mei 2027 | 0% | 0% | Not Started |
| MOP-09 | Dashboard Balancing RMPMFG P3 Digital & Data | PPIC | — | 31 Des 2026 | 100% | +54,3% | Completed |
| MOP-10 | Dashboard Monitoring Report P3 Digital & Data | All Dept. | — | 11 Des 2026 | 15% | -40,6% | Delayed |
| MOP-11 | Management Report P3 Digital & Data | Operations (COO) | — | 15 Jan 2027 | 100% | +78,7% | Completed |
| MOP-12 | Compliance (CPPOB, HACCP, ISO) P4 Quality & Compliance | QAQC | — | 30 Sep 2027 | 24% | +11,8% | On Track |
| MOP-13 | Create CCP Setiap Proses Produksi P4 Quality & Compliance | QAQC | — | 31 Des 2026 | 21,6% | -28,4% | Delayed |
| MOP-14 | Visual Standar Quality incl. FS P4 Quality & Compliance | QAQC | — | 26 Feb 2027 | 10% | +8,1% | On Track |
| MOP-15 | Demand Supply Planning (S&OP) P5 Supply Chain & Planning | PPIC | — | 31 Mar 2027 | 85% | +63,4% | On Track |
| MOP-16 | Vendor Scorecard Procurement P5 Supply Chain & Planning | Procurement | — | 29 Jan 2027 | 17,5% | -11,6% | At Risk |
| MOP-17 | Optimizing WH Occupancy & Racking P5 Supply Chain & Planning | Warehouse & Logistics | — | 31 Mar 2027 | 0% | -10,7% | At Risk |
| MOP-18 | Ramadhan Strategy P5 Supply Chain & Planning | Operations (COO) | — | 19 Mar 2027 | 0% | -13,5% | At Risk |
| MOP-19 | Sangiang (Layout, LT, Renov, Move) P6 Infrastructure & NPD | Engineering | — | 30 Jun 2027 | 7% | -9,4% | On Track |
| MOP-20 | Speed Up NPD–EPD + Dashboard (I&O) P6 Infrastructure & NPD | R&D | — | 31 Mar 2027 | 50,8% | +32,5% | On Track |
| MOP-21 | Cost Reduction HPP Produk >45% P2 Cost & Productivity | R&D | — | 30 Nov 2026 | 72% | -5,2% | On Track |
| MOP-22 | Efisiensi Gas P2 Cost & Productivity | Production | Yusuf Hamdani / Fajar | 31 Des 2026 | 0% | -63,6% | Delayed |
| MOP-23 | AHU Ruang Produksi P6 Infrastructure & NPD | Production | Agung / Yusuf Hamdani | 29 Jan 2027 | 0% | -52% | Delayed |
| MOP-24 | Coding Machine P2 Cost & Productivity | Production | Dewa / Yusuf Hamdani | 30 Sep 2026 | 0% | -100% | Delayed |
| MOP-25 | Machine Guidance & Part Management P2 Cost & Productivity | Production | Yusuf Hamdani / Heri | 29 Jan 2027 | 0% | -39,7% | Delayed |
| MOP-26 | Reject Kemasan/Packaging P2 Cost & Productivity | QAQC | Shafry / Rama | 31 Des 2026 | 0% | -50% | Delayed |
| MOP-27 | Water Heater untuk Cleaning P2 Cost & Productivity | Production | Yusuf Hamdani / Dimekk | 31 Des 2026 | 0% | -50% | Delayed |
| MOP-28 | Baking Mate Evaluation P2 Cost & Productivity | R&D | Shafry / Tri | 29 Jan 2027 | 0% | -18% | At Risk |
| MOP-29 | Climate Chamber - Uji stability NPD P6 Infrastructure & NPD | R&D | Nia / Adi | 29 Jan 2027 | 0% | -37,6% | Delayed |
| MOP-30 | Efisiensi Listrik P2 Cost & Productivity | Production | Dewa / Yusuf Hamdani | 29 Jan 2027 | 0% | -18% | At Risk |
| MOP-31 | Optimalisasi Akurasi Pengiriman P5 Supply Chain & Planning | Fulfillment | Sofi / Randa | 29 Jan 2027 | 0% | -18% | At Risk |
| MOP-32 | Optimalisasi Produktivitas Packing P2 Cost & Productivity | Fulfillment | Sofi / Randa | 29 Jan 2027 | 0% | -18% | At Risk |
| MOP-33 | K3 - APAR P4 Quality & Compliance | Fulfillment | Sofi / Dimekk | 31 Des 2026 | 0% | -26,7% | Delayed |
| MOP-34 | Perbaikan Area Picking P5 Supply Chain & Planning | Fulfillment | Sofi | 31 Des 2026 | 0% | -50% | Delayed |
| MOP-35 | Evaluasi Penggunaan Oven P2 Cost & Productivity | Production | Tarwipin / Dewa | 31 Des 2026 | 0% | -50% | Delayed |
| MOP-36 | Kapasitas Meja Resting P2 Cost & Productivity | Production | Yusuf Hamdani / Dewa | 30 Nov 2026 | 0% | -77,2% | Delayed |
| MOP-37 | Pengkodean Secara Batch P3 Digital & Data | Production | Bintang / Shafry | 30 Nov 2026 | 0% | -77,2% | Delayed |
| MOP-38 | Perubahan Metode Packing #1 P2 Cost & Productivity | Fulfillment | Sofi / Eva | 30 Nov 2026 | 0% | -78,7% | Delayed |
| MOP-39 | Pest Control & Hygiene Revamp P4 Quality & Compliance | QAQC | — | — | 0% | 0% | Not Started |
| MOP-40 | Facility & Working Env. Improvement P6 Infrastructure & NPD | Production | — | — | 0% | 0% | Not Started |
| MOP-41 | Traffic & Safety (K3) Marking P1 People & Culture | Engineering | — | — | 0% | 0% | Not Started |
| MOP-42 | Time & Motion Study (SKU Repack) P2 Cost & Productivity | Production | — | — | 0% | 0% | Not Started |
| MOP-43 | Maintenance System Std. P3 Digital & Data | Engineering | — | — | 0% | 0% | Not Started |
| MOP-44 | Sensory Expert & Lexicon Dev P1 People & Culture | R&D | — | — | 0% | 0% | Not Started |
| MOP-45 | Container Box Plastic Management P5 Supply Chain & Planning | Production | Ardiansah Setiawan | 07 Des 2026 | 89,3% | +89,3% | On Track |