Improvement Project

MOP-16Vendor Scorecard Procurement

At RiskTerakhir disinkron 18 Nov 2026, 13.44 WIB

Ringkasan

Dari spreadsheet

Progress

17,5%

Planned

29,1%

Selisih

-11,6%

Pilar
P5 Supply Chain & Planning
Departemen
Procurement
PIC
—
Prioritas
Medium
Mulai
19 Okt 2026
Selesai (rencana)
29 Jan 2027
Selesai (aktual)
—

Riwayat

  1. Pertama kali tercatat

    18 Nov 2026, 13.44 WIB

Milestone & task

Task / milestonePICBobotMulaiSelesai (rencana)ProgressStatus
Kriteria scorecard (QCDS)Procurement1505 Okt 202610 Okt 2026
100%
Completed
Kumpulkan data performa vendorProcurement2505 Okt 202631 Okt 2026
10%
Delayed
Evaluasi & ranking vendorProcurement3505 Okt 202631 Okt 2026
0%
Delayed
Review & action plan vendorProcurement2505 Okt 202631 Okt 2026
0%
Delayed

Analisis & rencana improvement

Diisi di aplikasi; tidak ada di spreadsheet dan tidak tertimpa sinkron.

Problem statement

Belum diisi.

Latar belakang

Belum diisi.

Root cause

Belum diisi.

Tujuan

Belum diisi.

Hasil yang diharapkan

Belum diisi.

Recovery action

Belum diisi.

Metode improvement

Belum diisi.

Dokumen & tautan terkait

Belum diisi.

Issue & risk

Tidak ada issue tercatat.

Meeting terkait

Tersedia setelah modul Meeting (Phase 4).