MOP-19Sangiang (Layout, LT, Renov, Move)
On TrackTerakhir disinkron 18 Nov 2026, 13.44 WIB
Ringkasan
Dari spreadsheet
Progress
7%
Planned
16,4%
Selisih
-9,4%
- Pilar
- P6 Infrastructure & NPD
- Departemen
- Engineering
- PIC
- —
- Prioritas
- High
- Mulai
- 05 Okt 2026
- Selesai (rencana)
- 30 Jun 2027
- Selesai (aktual)
- —
Riwayat
Pertama kali tercatat
18 Nov 2026, 13.44 WIB
Milestone & task
| Task / milestone | PIC | Bobot | Mulai | Selesai (rencana) | Progress | Status |
|---|---|---|---|---|---|---|
| Finalisasi layout & timeline Sangiang Fokus pada 8 building. Area gudang 900m persegi | COO + Production | 10 | 16 Sep 2026 | 31 Okt 2026 | 70% | Delayed |
| Perizinan & tender renovasi | COO + Production | 20 | 31 Okt 2026 | 15 Mar 2027 | 0% | At Risk |
| Renovasi fisik | COO + Production | 30 | 22 Mar 2027 | 31 Jul 2027 | 0% | Not Started |
| Relokasi mesin & peralatan dari Cp | COO + Production | 25 | 01 Jun 2027 | 31 Agu 2027 | 0% | Not Started |
| Commissioning & trial produksi | COO + Production | 15 | 31 Agu 2027 | 04 Sep 2027 | 0% | Not Started |
Analisis & rencana improvement
Diisi di aplikasi; tidak ada di spreadsheet dan tidak tertimpa sinkron.
Problem statement
Belum diisi.
Latar belakang
Belum diisi.
Root cause
Belum diisi.
Tujuan
Belum diisi.
Hasil yang diharapkan
Belum diisi.
Recovery action
Belum diisi.
Metode improvement
Belum diisi.
Dokumen & tautan terkait
Belum diisi.
Issue & risk
- Jadwal renovasi Sangiang tergantung perizinan; potensi mundurTerbuka
Head of Engineering · Jatuh tempo 13 Nov 2026