Improvement Project

MOP-015R Implementation

DelayedTerakhir disinkron 18 Nov 2026, 13.44 WIB

Ringkasan

Dari spreadsheet

Progress

29,7%

Planned

100%

Selisih

-70,3%

Pilar
P1 People & Culture
Departemen
QAQC
PIC
—
Prioritas
High
Mulai
21 Sep 2026
Selesai (rencana)
09 Nov 2026
Selesai (aktual)
—

Riwayat

  1. Pertama kali tercatat

    18 Nov 2026, 13.44 WIB

Milestone & task

Task / milestonePICBobotMulaiSelesai (rencana)ProgressStatus
Sosialisasi & training 5R

Sangiang, Fullfill, Joglo, DPR, Lab RnD, Cipondoh. Kurang Enginering

QAQC1021 Sep 202612 Okt 2026
86%
Delayed
Pembagian zona & PIC area

Kurang Enginering

QAQC2028 Sep 202619 Okt 2026
43%
Delayed
Ringkas-Rapi-Resik (red tag, labeling)All Dept.3013 Okt 202607 Nov 2026
0%
Delayed
Standardisasi (Rawat) & checklist

Form checklist sudah tersedia

QAQC2513 Okt 202631 Okt 2026
50%
Delayed
Audit 5R bulanan & sustain (Rajin)QAQC1502 Nov 202609 Nov 2026
0%
Delayed

Analisis & rencana improvement

Diisi di aplikasi; tidak ada di spreadsheet dan tidak tertimpa sinkron.

Problem statement

Belum diisi.

Latar belakang

Belum diisi.

Root cause

Belum diisi.

Tujuan

Belum diisi.

Hasil yang diharapkan

Belum diisi.

Recovery action

Belum diisi.

Metode improvement

Belum diisi.

Dokumen & tautan terkait

Belum diisi.

Issue & risk

Tidak ada issue tercatat.

Meeting terkait

Tersedia setelah modul Meeting (Phase 4).