Manufacturing Ops Strategic Project Control
SOURCE_1Google Spreadsheet (dibagikan lewat tautan)Tersambung
Spreadsheet Project Control (CI Lead), dibagikan lewat tautan sejak 18 Nov 2026 dan diunduh sebagai xlsx. Sheet: Project_List, Task_Detail, Issue_Log, Setting, dll.
Dataset
Task_Detail
Menampilkan 151–200 dari 206 baris
| Baris sheet | No | End | Bobot | Start | Status | Catatan | Kolom O | Dept PIC | Planned % | Progress % | Project ID | Nama Project | Durasi (hari) | Bobot× Progress | Task / Milestone | 2026-10-05T00:00:00.000Z | 2026-10-12T00:00:00.000Z | 2026-10-19T00:00:00.000Z | 2026-10-26T00:00:00.000Z | 2026-11-02T00:00:00.000Z | 2026-11-09T00:00:00.000Z | 2026-11-16T00:00:00.000Z | 2026-11-23T00:00:00.000Z | 2026-11-30T00:00:00.000Z | 2026-12-07T00:00:00.000Z | 2026-12-14T00:00:00.000Z | 2026-12-21T00:00:00.000Z | 2026-12-28T00:00:00.000Z | 2027-01-04T00:00:00.000Z | 2027-01-11T00:00:00.000Z | 2027-01-18T00:00:00.000Z | 2027-01-25T00:00:00.000Z | 2027-02-01T00:00:00.000Z | 2027-02-08T00:00:00.000Z | 2027-02-15T00:00:00.000Z | 2027-02-22T00:00:00.000Z | 2027-03-01T00:00:00.000Z | 2027-03-08T00:00:00.000Z | 2027-03-15T00:00:00.000Z | 2027-03-22T00:00:00.000Z | 2027-03-29T00:00:00.000Z | 2027-04-05T00:00:00.000Z | 2027-04-12T00:00:00.000Z | 2027-04-19T00:00:00.000Z | 2027-04-26T00:00:00.000Z | 2027-05-03T00:00:00.000Z | 2027-05-10T00:00:00.000Z | 2027-05-17T00:00:00.000Z | 2027-05-24T00:00:00.000Z | 2027-05-31T00:00:00.000Z | 2027-06-07T00:00:00.000Z | 2027-06-14T00:00:00.000Z | 2027-06-21T00:00:00.000Z | 2027-06-28T00:00:00.000Z | 2027-07-05T00:00:00.000Z | 2027-07-12T00:00:00.000Z | 2027-07-19T00:00:00.000Z | 2027-07-26T00:00:00.000Z | 2027-08-02T00:00:00.000Z | 2027-08-09T00:00:00.000Z | 2027-08-16T00:00:00.000Z | 2027-08-23T00:00:00.000Z | 2027-08-30T00:00:00.000Z | 2027-09-06T00:00:00.000Z | 2027-09-13T00:00:00.000Z | 2027-09-20T00:00:00.000Z | 2027-09-27T00:00:00.000Z |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 156 | 151 | 20 | Not Started | GA + WH Logistics | 0% | MOP-33 | K3 - APAR | Gap analysis kebutuhan APAR vs standar K3 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 157 | 152 | 20 | Not Started | GA + WH Logistics | 0% | MOP-33 | K3 - APAR | Pengadaan/refill APAR, penempatan & signage | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 158 | 153 | 20 | Not Started | GA + WH Logistics | 0% | MOP-33 | K3 - APAR | Kartu & jadwal inspeksi APAR bulanan | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 159 | 154 | 20 | Not Started | GA + WH Logistics | 0% | MOP-33 | K3 - APAR | Training penggunaan APAR | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 160 | 155 | 20 | Not Started | Fullfillment | 0% | 0% | MOP-34 | Perbaikan Area Picking | Assesment kondisi & layout area picking saat ini | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 161 | 156 | 20 | Not Started | Fullfillment | 0% | MOP-34 | Perbaikan Area Picking | Desain layout baru (tahap geser & rencana pindah ke Joglo) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 162 | 157 | 20 | Not Started | Fullfillment | 0% | MOP-34 | Perbaikan Area Picking | Penataan tahap 1: geser rak & slotting fast-moving | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 163 | 158 | 20 | Not Started | Fullfillment | 0% | MOP-34 | Perbaikan Area Picking | Persiapan & pindah area picking ke Joglo | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 164 | 159 | 20 | Not Started | Fullfillment | 0% | MOP-34 | Perbaikan Area Picking | Ukur waktu picking & evaluasi | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 165 | 160 | 20 | Not Started | Production + R&D | 0% | 0% | MOP-35 | Evaluasi Penggunaan Oven | Pengumpulan data pemakaian oven (jam operasi, batch, energi) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 166 | 161 | 20 | Not Started | Production + R&D | 0% | MOP-35 | Evaluasi Penggunaan Oven | Analisa utilisasi, yield & energi per batch | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 167 | 162 | 20 | Not Started | Production + R&D | 0% | MOP-35 | Evaluasi Penggunaan Oven | Rekomendasi jadwal/loading oven optimal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 168 | 163 | 20 | Not Started | Production + R&D | 0% | MOP-35 | Evaluasi Penggunaan Oven | Trial implementasi pola pemakaian oven baru | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 169 | 164 | 20 | Not Started | Production + R&D | 0% | MOP-35 | Evaluasi Penggunaan Oven | Evaluasi hasil & standardisasi | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 170 | 165 | 20 | Not Started | Engineering + Production | 0% | 0% | MOP-36 | Kapasitas Meja Resting | Data output & waktu resting per produk | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 171 | 166 | 20 | Not Started | Engineering + Production | 0% | MOP-36 | Kapasitas Meja Resting | Hitung kebutuhan kapasitas meja resting | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 172 | 167 | 20 | Not Started | Engineering + Production | 0% | MOP-36 | Kapasitas Meja Resting | Desain layout meja resting | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 173 | 168 | 20 | Not Started | Engineering + Production | 0% | MOP-36 | Kapasitas Meja Resting | Pengadaan/penataan meja resting | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 174 | 169 | 20 | Not Started | Engineering + Production | 0% | MOP-36 | Kapasitas Meja Resting | Verifikasi kapasitas vs output aktual | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 175 | 170 | 20 | Not Started | QAQC + R&D | 0% | 0% | MOP-37 | Pengkodean Secara Batch | Definisi format kode batch (1 shift 1 batch + jam) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 176 | 171 | 20 | Not Started | QAQC + R&D | 0% | MOP-37 | Pengkodean Secara Batch | Setting coding machine/printer sesuai format batch | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 177 | 172 | 20 | Not Started | QAQC + R&D | 0% | MOP-37 | Pengkodean Secara Batch | Integrasi kode batch dengan input hasil produksi di ERP | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 178 | 173 | 20 | Not Started | QAQC + R&D | 0% | MOP-37 | Pengkodean Secara Batch | Trial & sosialisasi ke operator | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 179 | 174 | 20 | Not Started | QAQC + R&D | 0% | MOP-37 | Pengkodean Secara Batch | Verifikasi traceability (uji telusur / mock recall) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 180 | 175 | 20 | Not Started | Fullfillment | 0% | 0% | MOP-38 | Perubahan Metode Packing #1 | Spesifikasi polymailer per SKU (ukuran, ketebalan) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 181 | 176 | 20 | Not Started | Fullfillment | 0% | 0% | MOP-38 | Perubahan Metode Packing #1 | Sourcing & sampling vendor polymailer | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 182 | 177 | 20 | Not Started | Fullfillment | 0% | MOP-38 | Perubahan Metode Packing #1 | Uji kemasan (drop test, kebocoran) & approval | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 183 | 178 | 20 | Not Started | Fullfillment | 0% | 0% | MOP-38 | Perubahan Metode Packing #1 | Implementasi bertahap per SKU | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 184 | 179 | 20 | Not Started | Fullfillment | 0% | 0% | MOP-38 | Perubahan Metode Packing #1 | Hitung realisasi saving vs target ±Rp61,7 jt/bulan | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 185 | 180 | 20 | Not Started | Minta penawaran harga vendor | GA | 0% | 0% | MOP-40 | Facility & Working Env. Improvement | Asesmen suhu gudang & pengajuan peredam | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 186 | 181 | 15 | Not Started | Data semua titik kran | Maintenance | 0% | 0% | MOP-40 | Facility & Working Env. Improvement | Perbaikan & penggantian kran air yang rusak | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 187 | 182 | 25 | Not Started | Fokus loker pria & produksi | GA | 0% | 0% | MOP-40 | Facility & Working Env. Improvement | Perbaikan pintu ruang ganti & kunci loker | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 188 | 183 | 40 | Not Started | Untuk mempermudah cleaning mixer | Maintenance | 0% | 0% | MOP-40 | Facility & Working Env. Improvement | Instalasi pipa air di area mixing | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 189 | 184 | 30 | Not Started | Warehouse Logistics | 0% | 0% | MOP-41 | Traffic & Safety (K3) Marking | Mapping layout pedestrian route & jalur material | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 190 | 185 | 20 | Not Started | Purchasing | 0% | 0% | MOP-41 | Traffic & Safety (K3) Marking | Pembelian cat epoxy / lakban safety | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 191 | 186 | 50 | Not Started | Dilakukan saat shift libur/kosong | Maintenance + GA | 0% | 0% | MOP-41 | Traffic & Safety (K3) Marking | Pengecatan marking line di area gudang & produksi | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 192 | 187 | 30 | Not Started | SKU repack prioritas | CI + Production | 0% | 0% | MOP-42 | Time & Motion Study (SKU Repack) | Observasi lapangan & perekaman video cycle time | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 193 | 188 | 40 | Not Started | CI | 0% | 0% | MOP-42 | Time & Motion Study (SKU Repack) | Analisa waste gerakan (Muda) & evaluasi waktu baku | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 194 | 189 | 30 | Not Started | CI + Production | 0% | 0% | MOP-42 | Time & Motion Study (SKU Repack) | Penetapan target output standar baru & sosialisasi | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 195 | 190 | 20 | Not Started | Sesuai dengan log di mesin | Maintenance | 0% | 0% | MOP-43 | Maintenance System Std. | Drafting form laporan harian teknisi | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 196 | 191 | 40 | Not Started | Maintenance + CI | 0% | 0% | MOP-43 | Maintenance System Std. | Kalibrasi data mesin aktual vs sistem pencatatan | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 197 | 192 | 40 | Not Started | Maintenance | 0% | 0% | MOP-43 | Maintenance System Std. | 5R di area workshop & penyusunan SOP maintenance | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 198 | 193 | 20 | Not Started | QC + HC | 0% | 0% | MOP-44 | Sensory Expert & Lexicon Dev | Pencarian silabus / vendor training sensory expert | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 199 | 194 | 30 | Not Started | Referensi dari produk exisitng | R&D + QC | 0% | 0% | MOP-44 | Sensory Expert & Lexicon Dev | Penyusunan Sensory Value Lexicon / Flavor Language | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 200 | 195 | 20 | Not Started | Beri penanda dedicated area | R&D + QC | 0% | 0% | MOP-44 | Sensory Expert & Lexicon Dev | Standarisasi showcase/chiller & rak retain sample | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 201 | 196 | 30 | Not Started | Target 3 panelis tersertifikasi | R&D + QC | 0% | 0% | MOP-44 | Sensory Expert & Lexicon Dev | Pelaksanaan training & sertifikasi internal panelis | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 202 | 197 | 20 | Not Started | Fokus dinding RND & plafon | GA + QAQC | 0% | 0% | MOP-39 | Pest Control & Hygiene Revamp | Inspeksi area (mapping lubang & sarang laba-laba) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 203 | 198 | 30 | Not Started | GA + Maintenance | 0% | 0% | MOP-39 | Pest Control & Hygiene Revamp | Penutupan dinding berlubang di RND | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 204 | 199 | 20 | Not Started | Prioritas area produksi & gudang | Cleaning Service | 0% | 0% | MOP-39 | Pest Control & Hygiene Revamp | Deep cleaning sarang laba-laba & ganti tempat sampah | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 205 | 200 | 30 | Not Started | Fokus pembasmian tikus | GA | 0% | 0% | MOP-39 | Pest Control & Hygiene Revamp | Evaluasi dan treatment Pest Control (vendor) |
Data mentah asli tersimpan apa adanya per pengambilan yang isinya berbeda (1 versi).Sebelumnya4 / 5Berikutnya