Manufacturing Ops Strategic Project Control
SOURCE_1Google Spreadsheet (dibagikan lewat tautan)Tersambung
Spreadsheet Project Control (CI Lead), dibagikan lewat tautan sejak 18 Nov 2026 dan diunduh sebagai xlsx. Sheet: Project_List, Task_Detail, Issue_Log, Setting, dll.
Dataset
Gantt_Project
Menampilkan 1–45 dari 45 baris
| Baris sheet | End | Pilar | Start | Status | Kolom I | Dept PIC | Progress | Project ID | Nama Project | 2026-10-05T00:00:00.000Z | 2026-10-12T00:00:00.000Z | 2026-10-19T00:00:00.000Z | 2026-10-26T00:00:00.000Z | 2026-11-02T00:00:00.000Z | 2026-11-09T00:00:00.000Z | 2026-11-16T00:00:00.000Z | 2026-11-23T00:00:00.000Z | 2026-11-30T00:00:00.000Z | 2026-12-07T00:00:00.000Z | 2026-12-14T00:00:00.000Z | 2026-12-21T00:00:00.000Z | 2026-12-28T00:00:00.000Z | 2027-01-04T00:00:00.000Z | 2027-01-11T00:00:00.000Z | 2027-01-18T00:00:00.000Z | 2027-01-25T00:00:00.000Z | 2027-02-01T00:00:00.000Z | 2027-02-08T00:00:00.000Z | 2027-02-15T00:00:00.000Z | 2027-02-22T00:00:00.000Z | 2027-03-01T00:00:00.000Z | 2027-03-08T00:00:00.000Z | 2027-03-15T00:00:00.000Z | 2027-03-22T00:00:00.000Z | 2027-03-29T00:00:00.000Z | 2027-04-05T00:00:00.000Z | 2027-04-12T00:00:00.000Z | 2027-04-19T00:00:00.000Z | 2027-04-26T00:00:00.000Z | 2027-05-03T00:00:00.000Z | 2027-05-10T00:00:00.000Z | 2027-05-17T00:00:00.000Z | 2027-05-24T00:00:00.000Z | 2027-05-31T00:00:00.000Z | 2027-06-07T00:00:00.000Z | 2027-06-14T00:00:00.000Z | 2027-06-21T00:00:00.000Z | 2027-06-28T00:00:00.000Z | 2027-07-05T00:00:00.000Z | 2027-07-12T00:00:00.000Z | 2027-07-19T00:00:00.000Z | 2027-07-26T00:00:00.000Z | 2027-08-02T00:00:00.000Z | 2027-08-09T00:00:00.000Z | 2027-08-16T00:00:00.000Z | 2027-08-23T00:00:00.000Z | 2027-08-30T00:00:00.000Z | 2027-09-06T00:00:00.000Z | 2027-09-13T00:00:00.000Z | 2027-09-20T00:00:00.000Z | 2027-09-27T00:00:00.000Z |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 7 | 09/11/2026 | P1 People & Culture | 21/09/2026 | Delayed | QAQC | 30% | MOP-01 | 5R Implementation | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 8 | 06/11/2026 | P1 People & Culture | 05/10/2026 | Delayed | COO + CI | 52% | MOP-02 | Bentuk CI + OBEYA | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 9 | 31/12/2026 | P1 People & Culture | 05/10/2026 | At Risk | QAQC + HC | 29% | MOP-03 | SOP Project (collab HC) | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 10 | 23/11/2026 | P2 Cost & Productivity | 05/10/2026 | Delayed | COO + Finance | 60% | MOP-04 | COGM Project | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 11 | 30/11/2026 | P2 Cost & Productivity | 05/10/2026 | Delayed | COO + PPIC | 0% | MOP-05 | Kurasi Pareto C by Manuf | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 12 | 26/02/2027 | P2 Cost & Productivity | 05/10/2026 | Delayed | Engineering + Production | 5% | MOP-06 | MC Development & Balancing | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 13 | 31/12/2026 | P3 Digital & Data | 05/10/2026 | Completed | COO + PPIC | 100% | MOP-07 | ERP v.1 – SPK Fully Operate | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 14 | 28/05/2027 | P3 Digital & Data | 04/01/2027 | Not Started | COO + IT | 0% | MOP-08 | Automate ERP B2B – COGM | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 15 | 31/12/2026 | P3 Digital & Data | 12/10/2026 | Completed | COO + PPIC | 100% | MOP-09 | Dashboard Balancing RMPMFG | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 16 | 11/12/2026 | P3 Digital & Data | 19/10/2026 | Delayed | COO + IT | 15% | MOP-10 | Dashboard Monitoring Report | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 17 | 15/01/2027 | P3 Digital & Data | 02/11/2026 | Completed | COO + IT | 100% | MOP-11 | Management Report | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 18 | 30/09/2027 | P4 Quality & Compliance | 05/10/2026 | On Track | COO + QAQC | 24% | MOP-12 | Compliance (CPPOB, HACCP, ISO) | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 19 | 31/12/2026 | P4 Quality & Compliance | 05/10/2026 | Delayed | QAQC + Production | 22% | MOP-13 | Create CCP Setiap Proses Produksi | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 20 | 26/02/2027 | P4 Quality & Compliance | 16/11/2026 | On Track | QAQC | 10% | MOP-14 | Visual Standar Quality incl. FS | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 21 | 31/03/2027 | P5 Supply Chain & Planning | 12/10/2026 | On Track | PPIC + Production | 85% | MOP-15 | Demand Supply Planning (S&OP) | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 22 | 29/01/2027 | P5 Supply Chain & Planning | 19/10/2026 | At Risk | Procurement | 18% | MOP-16 | Vendor Scorecard Procurement | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 23 | 31/03/2027 | P5 Supply Chain & Planning | 02/11/2026 | At Risk | Warehouse & Logistics | 0% | MOP-17 | Optimizing WH Occupancy & Racking | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 24 | 19/03/2027 | P5 Supply Chain & Planning | 30/10/2026 | At Risk | COO + Production + PPIC | 0% | MOP-18 | Ramadhan Strategy | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 25 | 30/06/2027 | P6 Infrastructure & NPD | 05/10/2026 | On Track | COO + Production | 7% | MOP-19 | Sangiang (Layout, LT, Renov, Move) | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 26 | 31/03/2027 | P6 Infrastructure & NPD | 19/10/2026 | On Track | COO + R&D | 51% | MOP-20 | Speed Up NPD–EPD + Dashboard (I&O) | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 27 | 30/11/2026 | P2 Cost & Productivity | 05/10/2026 | On Track | COO + R&D | 72% | MOP-21 | Cost Reduction HPP Produk >45% | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 28 | 31/12/2026 | P2 Cost & Productivity | 02/09/2026 | Delayed | Production | 0% | MOP-22 | Efisiensi Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 29 | 29/01/2027 | P6 Infrastructure & NPD | 31/08/2026 | Delayed | Production | 0% | MOP-23 | AHU Ruang Produksi | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 30 | 30/09/2026 | P2 Cost & Productivity | 01/09/2026 | Delayed | Production | 0% | MOP-24 | Coding Machine | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 31 | 29/01/2027 | P2 Cost & Productivity | 01/10/2026 | Delayed | Production | 0% | MOP-25 | Machine Guidance & Part Management | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 32 | 31/12/2026 | P2 Cost & Productivity | 05/10/2026 | Delayed | QAQC | 0% | MOP-26 | Reject Kemasan/Packaging | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 33 | 31/12/2026 | P2 Cost & Productivity | 05/10/2026 | Delayed | Production | 0% | MOP-27 | Water Heater untuk Cleaning | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 34 | 29/01/2027 | P2 Cost & Productivity | 02/11/2026 | At Risk | R&D | 0% | MOP-28 | Baking Mate Evaluation | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 35 | 29/01/2027 | P6 Infrastructure & NPD | 05/10/2026 | Delayed | R&D | 0% | MOP-29 | Climate Chamber - Uji stability NPD | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 36 | 29/01/2027 | P2 Cost & Productivity | 02/11/2026 | At Risk | Production | 0% | MOP-30 | Efisiensi Listrik | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 37 | 29/01/2027 | P5 Supply Chain & Planning | 02/11/2026 | At Risk | Fulfillment | 0% | MOP-31 | Optimalisasi Akurasi Pengiriman | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 38 | 29/01/2027 | P2 Cost & Productivity | 02/11/2026 | At Risk | Fulfillment | 0% | MOP-32 | Optimalisasi Produktivitas Packing | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 39 | 31/12/2026 | P4 Quality & Compliance | 02/11/2026 | Delayed | Fulfillment | 0% | MOP-33 | K3 - APAR | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 40 | 31/12/2026 | P5 Supply Chain & Planning | 05/10/2026 | Delayed | Fulfillment | 0% | MOP-34 | Perbaikan Area Picking | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 41 | 31/12/2026 | P2 Cost & Productivity | 05/10/2026 | Delayed | Production | 0% | MOP-35 | Evaluasi Penggunaan Oven | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 42 | 30/11/2026 | P2 Cost & Productivity | 05/10/2026 | Delayed | Production | 0% | MOP-36 | Kapasitas Meja Resting | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 43 | 30/11/2026 | P3 Digital & Data | 05/10/2026 | Delayed | Production | 0% | MOP-37 | Pengkodean Secara Batch | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 44 | 30/11/2026 | P2 Cost & Productivity | 01/10/2026 | Delayed | Fulfillment | 0% | MOP-38 | Perubahan Metode Packing #1 | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 45 | P4 Quality & Compliance | Not Started | QAQC | 0% | MOP-39 | Pest Control & Hygiene Revamp | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 46 | P6 Infrastructure & NPD | Not Started | Production | 0% | MOP-40 | Facility & Working Env. Improvement | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 47 | P1 People & Culture | Not Started | Engineering | 0% | MOP-41 | Traffic & Safety (K3) Marking | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 48 | P2 Cost & Productivity | Not Started | Production | 0% | MOP-42 | Time & Motion Study (SKU Repack) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 49 | P3 Digital & Data | Not Started | Engineering | 0% | MOP-43 | Maintenance System Std. | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 50 | P1 People & Culture | Not Started | R&D | 0% | MOP-44 | Sensory Expert & Lexicon Dev | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 51 | 07/12/2026 | P5 Supply Chain & Planning | 19/10/2026 | On Track | Production | 89% | MOP-45 | Container Box Plastic Management |
Data mentah asli tersimpan apa adanya per pengambilan yang isinya berbeda (1 versi).