Manufacturing Ops Strategic Project Control

SOURCE_1Google Spreadsheet (dibagikan lewat tautan)Tersambung

Spreadsheet Project Control (CI Lead), dibagikan lewat tautan sejak 18 Nov 2026 dan diunduh sebagai xlsx. Sheet: Project_List, Task_Detail, Issue_Log, Setting, dll.

Dataset

Dashboard

Menampilkan 1–33 dari 33 baris

Baris sheet3PilarJumlahAt RiskDelayedKolom JOn TrackCompletedAvg PlannedNot StartedAvg ProgressCompleted (2)
97P1 People & Culture51283%222%On Track
108P2 Cost & Productivity16311156%19%At Risk
1120P3 Digital & Data72342%245%Delayed
127P4 Quality & Compliance52223%111%Not Started
13P5 Supply Chain & Planning741220%27%On Hold
14P6 Infrastructure & NPD52231%112%Cancelled
22Ringkasan per Departemen
23DepartemenJumlahAt RiskDelayedOn TrackCompletedAvg PlannedNot StartedAvg Progress
24Operations (COO)411131%140%
25Production1218153%27%
26Engineering41123%23%
27QAQC713244%116%
28PPIC31239%95%
29Procurement1129%18%
30Warehouse & Logistics1111%0%
31Fulfillment52338%0%
32R&D612246%120%
33Finance0%0%
34HC0%0%
35All Dept.1156%15%
43Project Perlu Perhatian (Delayed / At Risk, urut variance terburuk)
44Project IDNama ProjectPlannedVarianceProgressDept PICStatus
45MOP-24Coding Machine100%-100%0%ProductionDelayed
46MOP-38Perubahan Metode Packing #179%-79%0%FulfillmentDelayed
47MOP-05Kurasi Pareto C by Manuf77%-77%0%R&DDelayed
48MOP-36Kapasitas Meja Resting77%-77%0%ProductionDelayed
49MOP-37Pengkodean Secara Batch77%-77%0%ProductionDelayed
50MOP-015R Implementation100%-70%30%QAQCDelayed
51MOP-22Efisiensi Gas64%-64%0%ProductionDelayed
52MOP-23AHU Ruang Produksi52%-52%0%ProductionDelayed
53MOP-26Reject Kemasan/Packaging50%-50%0%QAQCDelayed
54MOP-27Water Heater untuk Cleaning50%-50%0%ProductionDelayed
55Jika kosong = tidak ada project Delayed/At Risk per tanggal cut-off.
Data mentah asli tersimpan apa adanya per pengambilan yang isinya berbeda (1 versi).