Manufacturing Ops Strategic Project Control
SOURCE_1Google Spreadsheet (dibagikan lewat tautan)Tersambung
Spreadsheet Project Control (CI Lead), dibagikan lewat tautan sejak 18 Nov 2026 dan diunduh sebagai xlsx. Sheet: Project_List, Task_Detail, Issue_Log, Setting, dll.
Dataset
Dashboard
Menampilkan 1–33 dari 33 baris
| Baris sheet | 3 | Pilar | Jumlah | At Risk | Delayed | Kolom J | On Track | Completed | Avg Planned | Not Started | Avg Progress | Completed (2) |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 9 | 7 | P1 People & Culture | 5 | 1 | 2 | 83% | 2 | 22% | On Track | |||
| 10 | 8 | P2 Cost & Productivity | 16 | 3 | 11 | 1 | 56% | 1 | 9% | At Risk | ||
| 11 | 20 | P3 Digital & Data | 7 | 2 | 3 | 42% | 2 | 45% | Delayed | |||
| 12 | 7 | P4 Quality & Compliance | 5 | 2 | 2 | 23% | 1 | 11% | Not Started | |||
| 13 | P5 Supply Chain & Planning | 7 | 4 | 1 | 2 | 20% | 27% | On Hold | ||||
| 14 | P6 Infrastructure & NPD | 5 | 2 | 2 | 31% | 1 | 12% | Cancelled | ||||
| 22 | Ringkasan per Departemen | |||||||||||
| 23 | Departemen | Jumlah | At Risk | Delayed | On Track | Completed | Avg Planned | Not Started | Avg Progress | |||
| 24 | Operations (COO) | 4 | 1 | 1 | 1 | 31% | 1 | 40% | ||||
| 25 | Production | 12 | 1 | 8 | 1 | 53% | 2 | 7% | ||||
| 26 | Engineering | 4 | 1 | 1 | 23% | 2 | 3% | |||||
| 27 | QAQC | 7 | 1 | 3 | 2 | 44% | 1 | 16% | ||||
| 28 | PPIC | 3 | 1 | 2 | 39% | 95% | ||||||
| 29 | Procurement | 1 | 1 | 29% | 18% | |||||||
| 30 | Warehouse & Logistics | 1 | 1 | 11% | 0% | |||||||
| 31 | Fulfillment | 5 | 2 | 3 | 38% | 0% | ||||||
| 32 | R&D | 6 | 1 | 2 | 2 | 46% | 1 | 20% | ||||
| 33 | Finance | 0% | 0% | |||||||||
| 34 | HC | 0% | 0% | |||||||||
| 35 | All Dept. | 1 | 1 | 56% | 15% | |||||||
| 43 | Project Perlu Perhatian (Delayed / At Risk, urut variance terburuk) | |||||||||||
| 44 | Project ID | Nama Project | Planned | Variance | Progress | Dept PIC | Status | |||||
| 45 | MOP-24 | Coding Machine | 100% | -100% | 0% | Production | Delayed | |||||
| 46 | MOP-38 | Perubahan Metode Packing #1 | 79% | -79% | 0% | Fulfillment | Delayed | |||||
| 47 | MOP-05 | Kurasi Pareto C by Manuf | 77% | -77% | 0% | R&D | Delayed | |||||
| 48 | MOP-36 | Kapasitas Meja Resting | 77% | -77% | 0% | Production | Delayed | |||||
| 49 | MOP-37 | Pengkodean Secara Batch | 77% | -77% | 0% | Production | Delayed | |||||
| 50 | MOP-01 | 5R Implementation | 100% | -70% | 30% | QAQC | Delayed | |||||
| 51 | MOP-22 | Efisiensi Gas | 64% | -64% | 0% | Production | Delayed | |||||
| 52 | MOP-23 | AHU Ruang Produksi | 52% | -52% | 0% | Production | Delayed | |||||
| 53 | MOP-26 | Reject Kemasan/Packaging | 50% | -50% | 0% | QAQC | Delayed | |||||
| 54 | MOP-27 | Water Heater untuk Cleaning | 50% | -50% | 0% | Production | Delayed | |||||
| 55 | Jika kosong = tidak ada project Delayed/At Risk per tanggal cut-off. |
Data mentah asli tersimpan apa adanya per pengambilan yang isinya berbeda (1 versi).