SOURCE_1Google Spreadsheet (dibagikan lewat tautan)Tersambung

Spreadsheet Project Control (CI Lead), dibagikan lewat tautan sejak 18 Nov 2026 dan diunduh sebagai xlsx. Sheet: Project_List, Task_Detail, Issue_Log, Setting, dll.

Dataset

Task_Detail

Menampilkan 51–100 dari 206 baris

Baris sheetNoEndBobotStartStatusCatatanKolom ODept PICPlanned %Progress %Project IDNama ProjectDurasi (hari)Bobot× ProgressTask / Milestone2026-10-05T00:00:00.000Z2026-10-12T00:00:00.000Z2026-10-19T00:00:00.000Z2026-10-26T00:00:00.000Z2026-11-02T00:00:00.000Z2026-11-09T00:00:00.000Z2026-11-16T00:00:00.000Z2026-11-23T00:00:00.000Z2026-11-30T00:00:00.000Z2026-12-07T00:00:00.000Z2026-12-14T00:00:00.000Z2026-12-21T00:00:00.000Z2026-12-28T00:00:00.000Z2027-01-04T00:00:00.000Z2027-01-11T00:00:00.000Z2027-01-18T00:00:00.000Z2027-01-25T00:00:00.000Z2027-02-01T00:00:00.000Z2027-02-08T00:00:00.000Z2027-02-15T00:00:00.000Z2027-02-22T00:00:00.000Z2027-03-01T00:00:00.000Z2027-03-08T00:00:00.000Z2027-03-15T00:00:00.000Z2027-03-22T00:00:00.000Z2027-03-29T00:00:00.000Z2027-04-05T00:00:00.000Z2027-04-12T00:00:00.000Z2027-04-19T00:00:00.000Z2027-04-26T00:00:00.000Z2027-05-03T00:00:00.000Z2027-05-10T00:00:00.000Z2027-05-17T00:00:00.000Z2027-05-24T00:00:00.000Z2027-05-31T00:00:00.000Z2027-06-07T00:00:00.000Z2027-06-14T00:00:00.000Z2027-06-21T00:00:00.000Z2027-06-28T00:00:00.000Z2027-07-05T00:00:00.000Z2027-07-12T00:00:00.000Z2027-07-19T00:00:00.000Z2027-07-26T00:00:00.000Z2027-08-02T00:00:00.000Z2027-08-09T00:00:00.000Z2027-08-16T00:00:00.000Z2027-08-23T00:00:00.000Z2027-08-30T00:00:00.000Z2027-09-06T00:00:00.000Z2027-09-13T00:00:00.000Z2027-09-20T00:00:00.000Z2027-09-27T00:00:00.000Z
565109/11/20261016/09/2026DelayedClose sebelum 12 NovemberCOO + QAQC100%80%MOP-12Compliance (CPPOB, HACCP, ISO)558Gap assessment CPPOB/HACCP/ISO/SNI
575209/11/20262005/10/2026DelayedCOO + QAQC + GA100%80%MOP-12Compliance (CPPOB, HACCP, ISO)3616Dokumen & perbaikan fasilitas
585331/10/20263005/10/2026DelayedCOO + QAQC100%0%MOP-12Compliance (CPPOB, HACCP, ISO)27Implementasi & internal audit
595431/12/20272501/12/2026Not StartedBertahap dibagi menjadi per 3 bulanCOO + QAQC0%0%MOP-12Compliance (CPPOB, HACCP, ISO)396Pre-assessment / audit eksternal
605531/12/20271501/12/2026Not StartedCOO + QAQC0%0%MOP-12Compliance (CPPOB, HACCP, ISO)396Sertifikasi
615618/10/20261016/09/2026DelayedKurang SKQAQC + Production100%90%MOP-13Create CCP Setiap Proses Produksi339Tim HACCP & flow diagram proses
625730/11/20262016/09/2026DelayedCipondoh DoneQAQC + Production83%14%MOP-13Create CCP Setiap Proses Produksi762.8Hazard analysis per proses
635831/12/20263016/09/2026DelayedCipondoh DoneQAQC + Production59%14%MOP-13Create CCP Setiap Proses Produksi1074.2Penetapan CCP & batas kritis
645931/12/20262505/10/2026DelayedCipondoh DoneQAQC + Production50%14%MOP-13Create CCP Setiap Proses Produksi883.5Prosedur monitoring & corrective action
656031/12/20261516/09/2026DelayedCipondoh DoneQAQC + Production59%14%MOP-13Create CCP Setiap Proses Produksi1072.1Verifikasi & validasi CCP
666131/12/20261505/10/2026DelayedQAQC50%10%MOP-14Visual Standar Quality incl. FS881.5Definisi standar kualitas visual per produk
676231/12/20262505/10/2026DelayedQAQC50%10%MOP-14Visual Standar Quality incl. FS882.5Desain OK/NG board & signage FS
686331/12/20263505/10/2026DelayedQAQC50%10%MOP-14Visual Standar Quality incl. FS883.5Pemasangan di line
696431/12/20262505/10/2026DelayedQAQC50%10%MOP-14Visual Standar Quality incl. FS882.5Training operator & audit kepatuhan
706505/10/20261001/09/2026CompletedPPIC + Production100%100%MOP-15Demand Supply Planning (S&OP)3510Desain proses & kalender S&OP
716605/10/20262001/09/2026CompletedPPIC + Production100%100%MOP-15Demand Supply Planning (S&OP)3520Demand review (forecast baseline)
726705/10/20263001/09/2026CompletedPPIC + Production100%100%MOP-15Demand Supply Planning (S&OP)3530Supply review & capacity check
736809/10/20262501/10/2026CompletedBuat Kalender Meeting Rutin S&OP perbrandPPIC + Production100%100%MOP-15Demand Supply Planning (S&OP)925Executive S&OP rutin
746905/11/20261501/10/2026DelayedPPIC + Production100%0%MOP-15Demand Supply Planning (S&OP)36Ukur forecast accuracy
757010/10/20261505/10/2026CompletedProcurement100%100%MOP-16Vendor Scorecard Procurement615Kriteria scorecard (QCDS)
767131/10/20262505/10/2026DelayedProcurement100%10%MOP-16Vendor Scorecard Procurement272.5Kumpulkan data performa vendor
777231/10/20263505/10/2026DelayedProcurement100%0%MOP-16Vendor Scorecard Procurement27Evaluasi & ranking vendor
787331/10/20262505/10/2026DelayedProcurement100%0%MOP-16Vendor Scorecard Procurement27Review & action plan vendor
797413/10/20261006/10/2026DelayedCek WH Logistic teamWarehouse Logistics100%0%MOP-17Optimizing WH Occupancy & Racking8Audit kapasitas & occupancy gudang
807528/10/20262014/10/2026DelayedWarehouse Logistics100%0%MOP-17Optimizing WH Occupancy & Racking15Desain layout & slotting
817620/10/20263006/10/2026DelayedWarehouse Logistics100%0%MOP-17Optimizing WH Occupancy & Racking15Pengadaan & instalasi racking
827703/11/20262521/10/2026DelayedWarehouse Logistics100%0%MOP-17Optimizing WH Occupancy & Racking14Relokasi stok & update lokasi
837831/10/20261505/10/2026DelayedWarehouse Logistics100%0%MOP-17Optimizing WH Occupancy & Racking27Ukur occupancy & akurasi
847930/10/20261027/10/2026DelayedCOO + Production + PPIC100%0%MOP-18Ramadhan Strategy4Forecast demand Ramadhan per SKU
858002/12/20262030/10/2026DelayedCOO + Production + PPIC56%0%MOP-18Ramadhan Strategy34Rencana kapasitas & build-up stock
868120/01/20273024/11/2026Not StartedCOO + Production + PPIC0%0%MOP-18Ramadhan Strategy58Pengadaan RM/PM untuk peak
878202/03/20272512/01/2027Not StartedCOO + Production + PPIC0%0%MOP-18Ramadhan Strategy50Eksekusi produksi build-up
888319/03/20271522/02/2027Not StartedCOO + Production + PPIC0%0%MOP-18Ramadhan Strategy26Monitoring selama Ramadhan & review
898431/10/20261016/09/2026DelayedFokus pada 8 building. Area gudang 900m persegiCOO + Production100%70%MOP-19Sangiang (Layout, LT, Renov, Move)467Finalisasi layout & timeline Sangiang
908515/03/20272031/10/2026At RiskCOO + Production13%0%MOP-19Sangiang (Layout, LT, Renov, Move)136Perizinan & tender renovasi
918631/07/20273022/03/2027Not StartedCOO + Production0%0%MOP-19Sangiang (Layout, LT, Renov, Move)132Renovasi fisik
928731/08/20272501/06/2027Not StartedCOO + Production0%0%MOP-19Sangiang (Layout, LT, Renov, Move)92Relokasi mesin & peralatan dari Cp
938804/09/20271531/08/2027Not StartedCOO + Production0%0%MOP-19Sangiang (Layout, LT, Renov, Move)5Commissioning & trial produksi
948923/10/20261506/10/2026DelayedCOO + R&D100%80%MOP-20Speed Up NPD–EPD + Dashboard (I&O)1812Mapping proses NPD/EPD saat ini
959023/10/20262506/10/2026DelayedCOO + R&D100%75%MOP-20Speed Up NPD–EPD + Dashboard (I&O)1818.75Stage-gate & target lead time
969131/10/20263506/10/2026DelayedCOO + R&D100%50%MOP-20Speed Up NPD–EPD + Dashboard (I&O)2617.5Dashboard R&D (Internal & OEM)
979230/11/20262531/10/2026DelayedCOO + R&D58%10%MOP-20Speed Up NPD–EPD + Dashboard (I&O)312.5Implementasi & review pipeline bulanan
989331/10/20261020/10/2026DelayedCOO + R&D100%30%MOP-21Cost Reduction HPP Produk >45%123Analisis Pareto ABC SKU (volume & margin)
999407/11/20262020/10/2026CompletedDone tinggal menunggu surat dari BMCOO + R&D100%100%MOP-21Cost Reduction HPP Produk >45%1920Kurasi SKU kelas C (keep/improve/discontinue)
1009507/11/20263005/10/2026DelayedCOO + R&D100%70%MOP-21Cost Reduction HPP Produk >45%3421Identifikasi inisiatif penuruan HPP
1019607/11/20262528/09/2026DelayedCOO + R&D100%70%MOP-21Cost Reduction HPP Produk >45%4117.5Eksekusi inisiatif (material, yield, packaging)
1029707/11/20261505/10/2026DelayedCOO + R&D100%70%MOP-21Cost Reduction HPP Produk >45%3410.5Validasi saving & tracking
1039825Not StartedEngineering + Production0%0%MOP-22Efisiensi GasAssesment penggunaan gas untuk mesin oven
1049925Not StartedEngineering + Production0%0%MOP-22Efisiensi GasAssesment jalur pipe gas
10510025Not StartedEngineering + Production0%0%MOP-22Efisiensi GasRAB new design jalur pipa gas
Data mentah asli tersimpan apa adanya per pengambilan yang isinya berbeda (1 versi).Sebelumnya2 / 5Berikutnya