Manufacturing Ops Strategic Project Control
SOURCE_1Google Spreadsheet (dibagikan lewat tautan)Tersambung
Spreadsheet Project Control (CI Lead), dibagikan lewat tautan sejak 18 Nov 2026 dan diunduh sebagai xlsx. Sheet: Project_List, Task_Detail, Issue_Log, Setting, dll.
Dataset
Task_Detail
Menampilkan 201–206 dari 206 baris
| Baris sheet | No | End | Bobot | Start | Status | Catatan | Kolom O | Dept PIC | Planned % | Progress % | Project ID | Nama Project | Durasi (hari) | Bobot× Progress | Task / Milestone | 2026-10-05T00:00:00.000Z | 2026-10-12T00:00:00.000Z | 2026-10-19T00:00:00.000Z | 2026-10-26T00:00:00.000Z | 2026-11-02T00:00:00.000Z | 2026-11-09T00:00:00.000Z | 2026-11-16T00:00:00.000Z | 2026-11-23T00:00:00.000Z | 2026-11-30T00:00:00.000Z | 2026-12-07T00:00:00.000Z | 2026-12-14T00:00:00.000Z | 2026-12-21T00:00:00.000Z | 2026-12-28T00:00:00.000Z | 2027-01-04T00:00:00.000Z | 2027-01-11T00:00:00.000Z | 2027-01-18T00:00:00.000Z | 2027-01-25T00:00:00.000Z | 2027-02-01T00:00:00.000Z | 2027-02-08T00:00:00.000Z | 2027-02-15T00:00:00.000Z | 2027-02-22T00:00:00.000Z | 2027-03-01T00:00:00.000Z | 2027-03-08T00:00:00.000Z | 2027-03-15T00:00:00.000Z | 2027-03-22T00:00:00.000Z | 2027-03-29T00:00:00.000Z | 2027-04-05T00:00:00.000Z | 2027-04-12T00:00:00.000Z | 2027-04-19T00:00:00.000Z | 2027-04-26T00:00:00.000Z | 2027-05-03T00:00:00.000Z | 2027-05-10T00:00:00.000Z | 2027-05-17T00:00:00.000Z | 2027-05-24T00:00:00.000Z | 2027-05-31T00:00:00.000Z | 2027-06-07T00:00:00.000Z | 2027-06-14T00:00:00.000Z | 2027-06-21T00:00:00.000Z | 2027-06-28T00:00:00.000Z | 2027-07-05T00:00:00.000Z | 2027-07-12T00:00:00.000Z | 2027-07-19T00:00:00.000Z | 2027-07-26T00:00:00.000Z | 2027-08-02T00:00:00.000Z | 2027-08-09T00:00:00.000Z | 2027-08-16T00:00:00.000Z | 2027-08-23T00:00:00.000Z | 2027-08-30T00:00:00.000Z | 2027-09-06T00:00:00.000Z | 2027-09-13T00:00:00.000Z | 2027-09-20T00:00:00.000Z | 2027-09-27T00:00:00.000Z |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 206 | 201 | 27/10/2026 | 25 | 19/10/2026 | Delayed | Tercatat 4.557 dari 4.700 pcs (97%); sisa ±143 pcs (3%) belum berstiker/disensus | All Team Inventory + CI | 100% | 97% | MOP-45 | Container Box Plastic Management | 9 | 24.25 | Tahap 0: Label & kontainer (Hitung fisik, kode aplikasi, cetak & tempel stiker serentak 7 gudang) | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 207 | 202 | 26/10/2026 | 15 | 20/10/2026 | Completed | 5 dari 5 langkah selesai (100%) | All Team Inventory + CI | 100% | 100% | MOP-45 | Container Box Plastic Management | 7 | 15 | Tahap 1: Akun & master data (Setup gudang, akun petugas/supervisor, sopir & kendaraan) | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 208 | 203 | 01/11/2026 | 20 | 21/10/2026 | Completed | 100% terpasang (45/45 pembaruan aplikasi, SOP & IK Rev 03 di Drive, Traccar produksi aktif) | CI | 100% | 100% | MOP-45 | Container Box Plastic Management | 12 | 20 | Tahap 2: HP, lokasi & sistem aplikasi (Setup radius GPS, Traccar Client, SOP & IK Rev 03, 45 update fitur) | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 209 | 204 | 28/10/2026 | 15 | 21/10/2026 | Completed | 4 dari 4 langkah latihan selesai (100%); 47 trip selesai & 421 temuan berhasil diselesaikan | All Team Inventory + CI | 100% | 100% | MOP-45 | Container Box Plastic Management | 8 | 15 | Tahap 3: Latihan & simulasi operasional (Uji trip, muat, SJK, opname & penyelesaian temuan) | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 210 | 205 | 02/11/2026 | 15 | 31/10/2026 | Delayed | 2 dari 3 langkah selesai (67%); Go-Live Senin 2 Nov; tindak lanjut 293 temuan terbuka & 21 trip berjalan | All Team Inventory + CI | 100% | 67% | MOP-45 | Container Box Plastic Management | 3 | 10.05 | Tahap 4: Mulai sungguhan / Go-Live (Sensus titik nol stok, penyelesaian temuan & Go-Live trip pertama) | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 211 | 206 | 07/12/2026 | 10 | 03/11/2026 | On Track | 2 dari 4 langkah siap (50%); jadwal evaluasi minggu pertama & opname bulanan mulai 3 Nov | All Team Inventory + CI | 43% | 50% | MOP-45 | Container Box Plastic Management | 35 | 5 | Tahap 5: Rutin & evaluasi (Evaluasi minggu pertama, opname bulanan & audit kepatuhan berkelanjutan) |
Data mentah asli tersimpan apa adanya per pengambilan yang isinya berbeda (1 versi).Sebelumnya5 / 5