Manufacturing Ops Strategic Project Control
SOURCE_1Google Spreadsheet (dibagikan lewat tautan)Tersambung
Spreadsheet Project Control (CI Lead), dibagikan lewat tautan sejak 18 Nov 2026 dan diunduh sebagai xlsx. Sheet: Project_List, Task_Detail, Issue_Log, Setting, dll.
Dataset
Task_Detail
Menampilkan 51–100 dari 206 baris
| Baris sheet | No | End | Bobot | Start | Status | Catatan | Kolom O | Dept PIC | Planned % | Progress % | Project ID | Nama Project | Durasi (hari) | Bobot× Progress | Task / Milestone | 2026-10-05T00:00:00.000Z | 2026-10-12T00:00:00.000Z | 2026-10-19T00:00:00.000Z | 2026-10-26T00:00:00.000Z | 2026-11-02T00:00:00.000Z | 2026-11-09T00:00:00.000Z | 2026-11-16T00:00:00.000Z | 2026-11-23T00:00:00.000Z | 2026-11-30T00:00:00.000Z | 2026-12-07T00:00:00.000Z | 2026-12-14T00:00:00.000Z | 2026-12-21T00:00:00.000Z | 2026-12-28T00:00:00.000Z | 2027-01-04T00:00:00.000Z | 2027-01-11T00:00:00.000Z | 2027-01-18T00:00:00.000Z | 2027-01-25T00:00:00.000Z | 2027-02-01T00:00:00.000Z | 2027-02-08T00:00:00.000Z | 2027-02-15T00:00:00.000Z | 2027-02-22T00:00:00.000Z | 2027-03-01T00:00:00.000Z | 2027-03-08T00:00:00.000Z | 2027-03-15T00:00:00.000Z | 2027-03-22T00:00:00.000Z | 2027-03-29T00:00:00.000Z | 2027-04-05T00:00:00.000Z | 2027-04-12T00:00:00.000Z | 2027-04-19T00:00:00.000Z | 2027-04-26T00:00:00.000Z | 2027-05-03T00:00:00.000Z | 2027-05-10T00:00:00.000Z | 2027-05-17T00:00:00.000Z | 2027-05-24T00:00:00.000Z | 2027-05-31T00:00:00.000Z | 2027-06-07T00:00:00.000Z | 2027-06-14T00:00:00.000Z | 2027-06-21T00:00:00.000Z | 2027-06-28T00:00:00.000Z | 2027-07-05T00:00:00.000Z | 2027-07-12T00:00:00.000Z | 2027-07-19T00:00:00.000Z | 2027-07-26T00:00:00.000Z | 2027-08-02T00:00:00.000Z | 2027-08-09T00:00:00.000Z | 2027-08-16T00:00:00.000Z | 2027-08-23T00:00:00.000Z | 2027-08-30T00:00:00.000Z | 2027-09-06T00:00:00.000Z | 2027-09-13T00:00:00.000Z | 2027-09-20T00:00:00.000Z | 2027-09-27T00:00:00.000Z |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 56 | 51 | 09/11/2026 | 10 | 16/09/2026 | Delayed | Close sebelum 12 November | COO + QAQC | 100% | 80% | MOP-12 | Compliance (CPPOB, HACCP, ISO) | 55 | 8 | Gap assessment CPPOB/HACCP/ISO/SNI | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 57 | 52 | 09/11/2026 | 20 | 05/10/2026 | Delayed | COO + QAQC + GA | 100% | 80% | MOP-12 | Compliance (CPPOB, HACCP, ISO) | 36 | 16 | Dokumen & perbaikan fasilitas | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 58 | 53 | 31/10/2026 | 30 | 05/10/2026 | Delayed | COO + QAQC | 100% | 0% | MOP-12 | Compliance (CPPOB, HACCP, ISO) | 27 | Implementasi & internal audit | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 59 | 54 | 31/12/2027 | 25 | 01/12/2026 | Not Started | Bertahap dibagi menjadi per 3 bulan | COO + QAQC | 0% | 0% | MOP-12 | Compliance (CPPOB, HACCP, ISO) | 396 | Pre-assessment / audit eksternal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 60 | 55 | 31/12/2027 | 15 | 01/12/2026 | Not Started | COO + QAQC | 0% | 0% | MOP-12 | Compliance (CPPOB, HACCP, ISO) | 396 | Sertifikasi | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 61 | 56 | 18/10/2026 | 10 | 16/09/2026 | Delayed | Kurang SK | QAQC + Production | 100% | 90% | MOP-13 | Create CCP Setiap Proses Produksi | 33 | 9 | Tim HACCP & flow diagram proses | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 62 | 57 | 30/11/2026 | 20 | 16/09/2026 | Delayed | Cipondoh Done | QAQC + Production | 83% | 14% | MOP-13 | Create CCP Setiap Proses Produksi | 76 | 2.8 | Hazard analysis per proses | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 63 | 58 | 31/12/2026 | 30 | 16/09/2026 | Delayed | Cipondoh Done | QAQC + Production | 59% | 14% | MOP-13 | Create CCP Setiap Proses Produksi | 107 | 4.2 | Penetapan CCP & batas kritis | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 64 | 59 | 31/12/2026 | 25 | 05/10/2026 | Delayed | Cipondoh Done | QAQC + Production | 50% | 14% | MOP-13 | Create CCP Setiap Proses Produksi | 88 | 3.5 | Prosedur monitoring & corrective action | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 65 | 60 | 31/12/2026 | 15 | 16/09/2026 | Delayed | Cipondoh Done | QAQC + Production | 59% | 14% | MOP-13 | Create CCP Setiap Proses Produksi | 107 | 2.1 | Verifikasi & validasi CCP | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 66 | 61 | 31/12/2026 | 15 | 05/10/2026 | Delayed | QAQC | 50% | 10% | MOP-14 | Visual Standar Quality incl. FS | 88 | 1.5 | Definisi standar kualitas visual per produk | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 67 | 62 | 31/12/2026 | 25 | 05/10/2026 | Delayed | QAQC | 50% | 10% | MOP-14 | Visual Standar Quality incl. FS | 88 | 2.5 | Desain OK/NG board & signage FS | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 68 | 63 | 31/12/2026 | 35 | 05/10/2026 | Delayed | QAQC | 50% | 10% | MOP-14 | Visual Standar Quality incl. FS | 88 | 3.5 | Pemasangan di line | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 69 | 64 | 31/12/2026 | 25 | 05/10/2026 | Delayed | QAQC | 50% | 10% | MOP-14 | Visual Standar Quality incl. FS | 88 | 2.5 | Training operator & audit kepatuhan | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 70 | 65 | 05/10/2026 | 10 | 01/09/2026 | Completed | PPIC + Production | 100% | 100% | MOP-15 | Demand Supply Planning (S&OP) | 35 | 10 | Desain proses & kalender S&OP | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 71 | 66 | 05/10/2026 | 20 | 01/09/2026 | Completed | PPIC + Production | 100% | 100% | MOP-15 | Demand Supply Planning (S&OP) | 35 | 20 | Demand review (forecast baseline) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 72 | 67 | 05/10/2026 | 30 | 01/09/2026 | Completed | PPIC + Production | 100% | 100% | MOP-15 | Demand Supply Planning (S&OP) | 35 | 30 | Supply review & capacity check | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 73 | 68 | 09/10/2026 | 25 | 01/10/2026 | Completed | Buat Kalender Meeting Rutin S&OP perbrand | PPIC + Production | 100% | 100% | MOP-15 | Demand Supply Planning (S&OP) | 9 | 25 | Executive S&OP rutin | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 74 | 69 | 05/11/2026 | 15 | 01/10/2026 | Delayed | PPIC + Production | 100% | 0% | MOP-15 | Demand Supply Planning (S&OP) | 36 | Ukur forecast accuracy | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 75 | 70 | 10/10/2026 | 15 | 05/10/2026 | Completed | Procurement | 100% | 100% | MOP-16 | Vendor Scorecard Procurement | 6 | 15 | Kriteria scorecard (QCDS) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 76 | 71 | 31/10/2026 | 25 | 05/10/2026 | Delayed | Procurement | 100% | 10% | MOP-16 | Vendor Scorecard Procurement | 27 | 2.5 | Kumpulkan data performa vendor | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 77 | 72 | 31/10/2026 | 35 | 05/10/2026 | Delayed | Procurement | 100% | 0% | MOP-16 | Vendor Scorecard Procurement | 27 | Evaluasi & ranking vendor | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 78 | 73 | 31/10/2026 | 25 | 05/10/2026 | Delayed | Procurement | 100% | 0% | MOP-16 | Vendor Scorecard Procurement | 27 | Review & action plan vendor | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 79 | 74 | 13/10/2026 | 10 | 06/10/2026 | Delayed | Cek WH Logistic team | Warehouse Logistics | 100% | 0% | MOP-17 | Optimizing WH Occupancy & Racking | 8 | Audit kapasitas & occupancy gudang | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 80 | 75 | 28/10/2026 | 20 | 14/10/2026 | Delayed | Warehouse Logistics | 100% | 0% | MOP-17 | Optimizing WH Occupancy & Racking | 15 | Desain layout & slotting | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 81 | 76 | 20/10/2026 | 30 | 06/10/2026 | Delayed | Warehouse Logistics | 100% | 0% | MOP-17 | Optimizing WH Occupancy & Racking | 15 | Pengadaan & instalasi racking | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 82 | 77 | 03/11/2026 | 25 | 21/10/2026 | Delayed | Warehouse Logistics | 100% | 0% | MOP-17 | Optimizing WH Occupancy & Racking | 14 | Relokasi stok & update lokasi | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 83 | 78 | 31/10/2026 | 15 | 05/10/2026 | Delayed | Warehouse Logistics | 100% | 0% | MOP-17 | Optimizing WH Occupancy & Racking | 27 | Ukur occupancy & akurasi | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 84 | 79 | 30/10/2026 | 10 | 27/10/2026 | Delayed | COO + Production + PPIC | 100% | 0% | MOP-18 | Ramadhan Strategy | 4 | Forecast demand Ramadhan per SKU | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 85 | 80 | 02/12/2026 | 20 | 30/10/2026 | Delayed | COO + Production + PPIC | 56% | 0% | MOP-18 | Ramadhan Strategy | 34 | Rencana kapasitas & build-up stock | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 86 | 81 | 20/01/2027 | 30 | 24/11/2026 | Not Started | COO + Production + PPIC | 0% | 0% | MOP-18 | Ramadhan Strategy | 58 | Pengadaan RM/PM untuk peak | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 87 | 82 | 02/03/2027 | 25 | 12/01/2027 | Not Started | COO + Production + PPIC | 0% | 0% | MOP-18 | Ramadhan Strategy | 50 | Eksekusi produksi build-up | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 88 | 83 | 19/03/2027 | 15 | 22/02/2027 | Not Started | COO + Production + PPIC | 0% | 0% | MOP-18 | Ramadhan Strategy | 26 | Monitoring selama Ramadhan & review | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 89 | 84 | 31/10/2026 | 10 | 16/09/2026 | Delayed | Fokus pada 8 building. Area gudang 900m persegi | COO + Production | 100% | 70% | MOP-19 | Sangiang (Layout, LT, Renov, Move) | 46 | 7 | Finalisasi layout & timeline Sangiang | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 90 | 85 | 15/03/2027 | 20 | 31/10/2026 | At Risk | COO + Production | 13% | 0% | MOP-19 | Sangiang (Layout, LT, Renov, Move) | 136 | Perizinan & tender renovasi | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 91 | 86 | 31/07/2027 | 30 | 22/03/2027 | Not Started | COO + Production | 0% | 0% | MOP-19 | Sangiang (Layout, LT, Renov, Move) | 132 | Renovasi fisik | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 92 | 87 | 31/08/2027 | 25 | 01/06/2027 | Not Started | COO + Production | 0% | 0% | MOP-19 | Sangiang (Layout, LT, Renov, Move) | 92 | Relokasi mesin & peralatan dari Cp | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 93 | 88 | 04/09/2027 | 15 | 31/08/2027 | Not Started | COO + Production | 0% | 0% | MOP-19 | Sangiang (Layout, LT, Renov, Move) | 5 | Commissioning & trial produksi | |||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 94 | 89 | 23/10/2026 | 15 | 06/10/2026 | Delayed | COO + R&D | 100% | 80% | MOP-20 | Speed Up NPD–EPD + Dashboard (I&O) | 18 | 12 | Mapping proses NPD/EPD saat ini | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 95 | 90 | 23/10/2026 | 25 | 06/10/2026 | Delayed | COO + R&D | 100% | 75% | MOP-20 | Speed Up NPD–EPD + Dashboard (I&O) | 18 | 18.75 | Stage-gate & target lead time | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 96 | 91 | 31/10/2026 | 35 | 06/10/2026 | Delayed | COO + R&D | 100% | 50% | MOP-20 | Speed Up NPD–EPD + Dashboard (I&O) | 26 | 17.5 | Dashboard R&D (Internal & OEM) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 97 | 92 | 30/11/2026 | 25 | 31/10/2026 | Delayed | COO + R&D | 58% | 10% | MOP-20 | Speed Up NPD–EPD + Dashboard (I&O) | 31 | 2.5 | Implementasi & review pipeline bulanan | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 98 | 93 | 31/10/2026 | 10 | 20/10/2026 | Delayed | COO + R&D | 100% | 30% | MOP-21 | Cost Reduction HPP Produk >45% | 12 | 3 | Analisis Pareto ABC SKU (volume & margin) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 99 | 94 | 07/11/2026 | 20 | 20/10/2026 | Completed | Done tinggal menunggu surat dari BM | COO + R&D | 100% | 100% | MOP-21 | Cost Reduction HPP Produk >45% | 19 | 20 | Kurasi SKU kelas C (keep/improve/discontinue) | |||||||||||||||||||||||||||||||||||||||||||||||||||||
| 100 | 95 | 07/11/2026 | 30 | 05/10/2026 | Delayed | COO + R&D | 100% | 70% | MOP-21 | Cost Reduction HPP Produk >45% | 34 | 21 | Identifikasi inisiatif penuruan HPP | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 101 | 96 | 07/11/2026 | 25 | 28/09/2026 | Delayed | COO + R&D | 100% | 70% | MOP-21 | Cost Reduction HPP Produk >45% | 41 | 17.5 | Eksekusi inisiatif (material, yield, packaging) | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 102 | 97 | 07/11/2026 | 15 | 05/10/2026 | Delayed | COO + R&D | 100% | 70% | MOP-21 | Cost Reduction HPP Produk >45% | 34 | 10.5 | Validasi saving & tracking | ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 103 | 98 | 25 | Not Started | Engineering + Production | 0% | 0% | MOP-22 | Efisiensi Gas | Assesment penggunaan gas untuk mesin oven | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 104 | 99 | 25 | Not Started | Engineering + Production | 0% | 0% | MOP-22 | Efisiensi Gas | Assesment jalur pipe gas | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 105 | 100 | 25 | Not Started | Engineering + Production | 0% | 0% | MOP-22 | Efisiensi Gas | RAB new design jalur pipa gas |
Data mentah asli tersimpan apa adanya per pengambilan yang isinya berbeda (1 versi).Sebelumnya2 / 5Berikutnya