Improvement Project

Data project dibaca dari spreadsheet Project Control, yang tetap menjadi sumber kebenaran.

20 project

KodeNama projectDepartemenPICSelesai (rencana)ProgressSelisihStatus
MOP-015R Implementation

P1 People & Culture

QAQC—09 Nov 2026
29,7%
-70,3%Delayed
MOP-02Bentuk CI + OBEYA

P1 People & Culture

COO + CI—06 Nov 2026
51,5%
-48,5%Delayed
MOP-04COGM Project

P2 Cost & Productivity

Operations (COO)—23 Nov 2026
60%
-28%Delayed
MOP-05Kurasi Pareto C by Manuf

P2 Cost & Productivity

R&D—30 Nov 2026
0%
-77,2%Delayed
MOP-06MC Development & Balancing

P2 Cost & Productivity

Engineering—26 Feb 2027
5%
-25,3%Delayed
MOP-10Dashboard Monitoring Report

P3 Digital & Data

All Dept.—11 Des 2026
15%
-40,6%Delayed
MOP-13Create CCP Setiap Proses Produksi

P4 Quality & Compliance

QAQC—31 Des 2026
21,6%
-28,4%Delayed
MOP-22Efisiensi Gas

P2 Cost & Productivity

ProductionYusuf Hamdani / Fajar31 Des 2026
0%
-63,6%Delayed
MOP-23AHU Ruang Produksi

P6 Infrastructure & NPD

ProductionAgung / Yusuf Hamdani29 Jan 2027
0%
-52%Delayed
MOP-24Coding Machine

P2 Cost & Productivity

ProductionDewa / Yusuf Hamdani30 Sep 2026
0%
-100%Delayed
MOP-25Machine Guidance & Part Management

P2 Cost & Productivity

ProductionYusuf Hamdani / Heri29 Jan 2027
0%
-39,7%Delayed
MOP-26Reject Kemasan/Packaging

P2 Cost & Productivity

QAQCShafry / Rama31 Des 2026
0%
-50%Delayed
MOP-27Water Heater untuk Cleaning

P2 Cost & Productivity

ProductionYusuf Hamdani / Dimekk31 Des 2026
0%
-50%Delayed
MOP-29Climate Chamber - Uji stability NPD

P6 Infrastructure & NPD

R&DNia / Adi29 Jan 2027
0%
-37,6%Delayed
MOP-33K3 - APAR

P4 Quality & Compliance

FulfillmentSofi / Dimekk31 Des 2026
0%
-26,7%Delayed
MOP-34Perbaikan Area Picking

P5 Supply Chain & Planning

FulfillmentSofi31 Des 2026
0%
-50%Delayed
MOP-35Evaluasi Penggunaan Oven

P2 Cost & Productivity

ProductionTarwipin / Dewa31 Des 2026
0%
-50%Delayed
MOP-36Kapasitas Meja Resting

P2 Cost & Productivity

ProductionYusuf Hamdani / Dewa30 Nov 2026
0%
-77,2%Delayed
MOP-37Pengkodean Secara Batch

P3 Digital & Data

ProductionBintang / Shafry30 Nov 2026
0%
-77,2%Delayed
MOP-38Perubahan Metode Packing #1

P2 Cost & Productivity

FulfillmentSofi / Eva30 Nov 2026
0%
-78,7%Delayed