Improvement Project
Data project dibaca dari spreadsheet Project Control, yang tetap menjadi sumber kebenaran.
8 project
| Kode | Nama project | Departemen | PIC | Selesai (rencana) | Progress | Selisih | Status |
|---|---|---|---|---|---|---|---|
| MOP-03 | SOP Project (collab HC) P1 People & Culture | QAQC | — | 31 Des 2026 | 29% | -21% | At Risk |
| MOP-16 | Vendor Scorecard Procurement P5 Supply Chain & Planning | Procurement | — | 29 Jan 2027 | 17,5% | -11,6% | At Risk |
| MOP-17 | Optimizing WH Occupancy & Racking P5 Supply Chain & Planning | Warehouse & Logistics | — | 31 Mar 2027 | 0% | -10,7% | At Risk |
| MOP-18 | Ramadhan Strategy P5 Supply Chain & Planning | Operations (COO) | — | 19 Mar 2027 | 0% | -13,5% | At Risk |
| MOP-28 | Baking Mate Evaluation P2 Cost & Productivity | R&D | Shafry / Tri | 29 Jan 2027 | 0% | -18% | At Risk |
| MOP-30 | Efisiensi Listrik P2 Cost & Productivity | Production | Dewa / Yusuf Hamdani | 29 Jan 2027 | 0% | -18% | At Risk |
| MOP-31 | Optimalisasi Akurasi Pengiriman P5 Supply Chain & Planning | Fulfillment | Sofi / Randa | 29 Jan 2027 | 0% | -18% | At Risk |
| MOP-32 | Optimalisasi Produktivitas Packing P2 Cost & Productivity | Fulfillment | Sofi / Randa | 29 Jan 2027 | 0% | -18% | At Risk |