Tracker SOP, perbaikan ERP, dan semua tenggat CI Hub di satu tempat.
Dari data CI Hub · diperbarui 20 Nov 2026 06:11
| Kode | Tenggat | Jenis | Divisi | PIC | Tahap | Progres | Target | Ketepatan |
|---|---|---|---|---|---|---|---|---|
| MOP-11 | Management Report | Project | Operations (COO) | — | Selesai | 100% | 6 Okt 2026 | Isi tgl selesai |
| MOP-09 | Dashboard Balancing RMPMFG | Project | PPIC | — | Selesai | 100% | 6 Nov 2026 | Isi tgl selesai |
| MOP-07 | ERP v.1 – SPK Fully Operate | Project | Operations (COO) | — | Selesai | 100% | 17 Nov 2026 | Isi tgl selesai |
| MOP-01 | Sosialisasi & training 5R | Task | QAQC | QAQC | Berjalan | 86% | 27 Nov 2026 | Mendekati target |
| MOP-20 | Mapping proses NPD/EPD saat ini | Task | R&D | COO + R&D | Berjalan | 80% | 27 Nov 2026 | Mendekati target |
| MOP-20 | Stage-gate & target lead time | Task | R&D | COO + R&D | Berjalan | 75% | 27 Nov 2026 | Mendekati target |
| MOP-02 | Setup ruang OBEYA & visual board | Task | Operations (COO) | COO + CI | Berjalan | 70% | 28 Nov 2026 | Sesuai jadwal |
| MOP-03 | Template SOP & prioritas proses kritis (dengan HC) | Task | QAQC | QAQC + HC | Berjalan | 80% | 28 Nov 2026 | Sesuai jadwal |
| MOP-12 | Dokumen & perbaikan fasilitas | Task | QAQC | COO + QAQC + GA | Berjalan | 80% | 30 Nov 2026 | Sesuai jadwal |
| MOP-21 | Identifikasi SKU dengan HPP >45% | Task | R&D | COO + R&D | Berjalan | 30% | 1 Des 2026 | Sesuai jadwal |
| MOP-02 | KPI & ritme meeting OBEYA | Task | Operations (COO) | COO + CI | Berjalan | 50% | 2 Des 2026 | Sesuai jadwal |
| MOP-02 | Pilot kaizen pertama | Task | Operations (COO) | COO + CI | Berjalan | 50% | 2 Des 2026 | Sesuai jadwal |
| MOP-12 | Gap assessment CPPOB/HACCP/ISO/SNI | Task | QAQC | COO + QAQC | Berjalan | 80% | 3 Des 2026 | Sesuai jadwal |
| MOP-16 | Kumpulkan data performa vendor | Task | Procurement | Procurement | Berjalan | 10% | 3 Des 2026 | Sesuai jadwal |
| MOP-21 | Identifikasi inisiatif penurunan HPP | Task | R&D | COO + R&D | Berjalan | 70% | 3 Des 2026 | Sesuai jadwal |
| MOP-21 | Validasi saving & tracking | Task | R&D | COO + R&D | Berjalan | 70% | 3 Des 2026 | Sesuai jadwal |
| MOP-06 | Time study & mapping kapasitas line | Task | Engineering | Engineering + Production | Berjalan | 50% | 5 Des 2026 | Sesuai jadwal |
| MOP-20 | Dashboard R&D (Internal & OEM) | Task | R&D | COO + R&D | Berjalan | 50% | 5 Des 2026 | Sesuai jadwal |
| MOP-21 | Cost Reduction HPP Produk >45% | Project | R&D | — | Berjalan | 72% | 5 Des 2026 | Sesuai jadwal |
| MOP-21 | Eksekusi inisiatif (material, yield, packaging) | Task | R&D | COO + R&D | Berjalan | 70% | 5 Des 2026 | Sesuai jadwal |
| MOP-19 | Finalisasi layout & timeline Sangiang | Task | Engineering | COO + Production | Berjalan | 70% | 6 Des 2026 | Sesuai jadwal |
| MOP-02 | Bentuk CI + OBEYA | Project | Operations (COO) | Ardiansah S | Berjalan | 52% | 7 Des 2026 | Sesuai jadwal |
| MOP-02 | Review & rollout | Task | Operations (COO) | COO + CI | Belum Mulai | 0% | 7 Des 2026 | Sesuai jadwal |
| MOP-04 | Validasi vs laporan keuangan | Task | Operations (COO) | COO + Finance | Belum Mulai | 0% | 7 Des 2026 | Sesuai jadwal |
| MOP-10 | Tentukan KPI harian - bulanan setiap dept. | Task | All Dept. | COO + IT | Berjalan | 50% | 7 Des 2026 | Sesuai jadwal |
| MOP-10 | Template input data | Task | All Dept. | COO + IT | Belum Mulai | 0% | 7 Des 2026 | Sesuai jadwal |
| MOP-16 | Evaluasi & ranking vendor | Task | Procurement | Procurement | Belum Mulai | 0% | 7 Des 2026 | Sesuai jadwal |
| MOP-16 | Review & action plan vendor | Task | Procurement | Procurement | Belum Mulai | 0% | 7 Des 2026 | Sesuai jadwal |
| MOP-45 | Container Box Plastic Management | Project | Warehouse & Logistics | Ardiansah Setiawan | Berjalan | 86% | 7 Des 2026 | Sesuai jadwal |
| MOP-45 | Tahap 5: Rutin & evaluasi (Evaluasi minggu pertama, opname bulanan & audit kepatuhan berkelanjutan) | Task | Warehouse & Logistics | All Team Inventory + CI | Berjalan | 50% | 7 Des 2026 | Sesuai jadwal |
| MOP-45 | Tahap 6: Pencucian rutin (jadwal & pelaksanaan pencucian container box) | Task | Warehouse & Logistics | All Team Inventory + CI | Belum Mulai | 0% | 7 Des 2026 | Sesuai jadwal |
| MOP-04 | COGM Project | Project | Operations (COO) | — | Berjalan | 60% | 14 Des 2026 | Sesuai jadwal |
| MOP-04 | Rilis report COGM bulanan | Task | Operations (COO) | COO + Finance | Belum Mulai | 0% | 14 Des 2026 | Sesuai jadwal |
| MOP-06 | Identifikasi bottleneck & line balancing | Task | Engineering | Engineering + Production | Belum Mulai | 0% | 18 Des 2026 | Sesuai jadwal |
| MOP-03 | Drafting SOP per departemen | Task | QAQC | QAQC + HC | Berjalan | 10% | 19 Des 2026 | Sesuai jadwal |
| MOP-05 | Eksekusi & ukur dampak ke stok dan okupansi gudang | Task | PPIC | COO + PPIC | Berjalan | 50% | 19 Des 2026 | Sesuai jadwal |
| MOP-12 | Implementasi & internal audit | Task | QAQC | COO + QAQC | Belum Mulai | 0% | 19 Des 2026 | Sesuai jadwal |
| MOP-01 | 5R Implementation | Project | QAQC | Shafry | Berjalan | 30% | 20 Des 2026 | Sesuai jadwal |
| MOP-01 | Pembagian zona & PIC area | Task | QAQC | QAQC | Berjalan | 43% | 20 Des 2026 | Sesuai jadwal |
| MOP-01 | Ringkas-Rapi-Resik (red tag, labeling) | Task | QAQC | All Dept. | Belum Mulai | 0% | 20 Des 2026 | Sesuai jadwal |
| MOP-01 | Standardisasi (Rawat) & checklist | Task | QAQC | QAQC | Berjalan | 50% | 20 Des 2026 | Sesuai jadwal |
| MOP-01 | Audit 5R bulanan & sustain (Rajin) | Task | QAQC | QAQC | Belum Mulai | 0% | 20 Des 2026 | Sesuai jadwal |
| MOP-20 | Speed Up NPD–EPD + Dashboard (I&O) | Project | R&D | — | Berjalan | 51% | 20 Des 2026 | Sesuai jadwal |
| MOP-20 | Implementasi & review pipeline bulanan | Task | R&D | COO + R&D | Berjalan | 10% | 20 Des 2026 | Sesuai jadwal |
| MOP-10 | Bangun dashboard dengan IT terintegrasi ERP | Task | All Dept. | COO + IT | Belum Mulai | 0% | 21 Des 2026 | Sesuai jadwal |
| MOP-15 | Demand Supply Planning (S&OP) | Project | PPIC | Yayat | Berjalan | 85% | 28 Des 2026 | Sesuai jadwal |
| MOP-13 | Create CCP Setiap Proses Produksi | Project | QAQC | — | Berjalan | 22% | 31 Des 2026 | Sesuai jadwal |
| MOP-13 | Tim HACCP & flow diagram proses | Task | QAQC | QAQC + Production | Berjalan | 90% | 31 Des 2026 | Sesuai jadwal |
| MOP-13 | Hazard analysis per proses | Task | QAQC | QAQC + Production | Berjalan | 14% | 31 Des 2026 | Sesuai jadwal |
| MOP-13 | Penetapan CCP & batas kritis | Task | QAQC | QAQC + Production | Berjalan | 14% | 31 Des 2026 | Sesuai jadwal |
| MOP-13 | Prosedur monitoring & corrective action | Task | QAQC | QAQC + Production | Berjalan | 14% | 31 Des 2026 | Sesuai jadwal |
| MOP-13 | Verifikasi & validasi CCP | Task | QAQC | QAQC + Production | Berjalan | 14% | 31 Des 2026 | Sesuai jadwal |
| MOP-15 | Ukur forecast accuracy | Task | PPIC | PPIC + Production | Belum Mulai | 0% | 31 Des 2026 | Sesuai jadwal |
| MOP-10 | Dashboard Monitoring Report | Project | All Dept. | Imam | Berjalan | 8% | 8 Jan 2027 | Sesuai jadwal |
| MOP-10 | Go-live & daily review | Task | All Dept. | COO + IT | Belum Mulai | 0% | 8 Jan 2027 | Sesuai jadwal |
| MOP-03 | Review, approval & dokumentasi | Task | QAQC | QAQC + HC | Belum Mulai | 0% | 16 Jan 2027 | Sesuai jadwal |
| MOP-16 | Vendor Scorecard Procurement | Project | Procurement | Imam | Berjalan | 18% | 29 Jan 2027 | Sesuai jadwal |
| MOP-14 | Visual Standar Quality incl. FS | Project | QAQC | — | Berjalan | 10% | 10 Feb 2027 | Sesuai jadwal |
| MOP-14 | Definisi standar kualitas visual per produk | Task | QAQC | QAQC | Berjalan | 10% | 10 Feb 2027 | Sesuai jadwal |
| MOP-14 | Desain OK/NG board & signage FS | Task | QAQC | QAQC | Berjalan | 10% | 10 Feb 2027 | Sesuai jadwal |
| MOP-14 | Pemasangan di line | Task | QAQC | QAQC | Berjalan | 10% | 10 Feb 2027 | Sesuai jadwal |
| MOP-14 | Training operator & audit kepatuhan | Task | QAQC | QAQC | Berjalan | 10% | 10 Feb 2027 | Sesuai jadwal |
| MOP-03 | SOP Project (collab HC) | Project | QAQC | — | Berjalan | 29% | 16 Feb 2027 | Sesuai jadwal |
| MOP-03 | Sosialisasi & training SOP | Task | QAQC | QAQC + HC | Belum Mulai | 0% | 16 Feb 2027 | Sesuai jadwal |
| MOP-06 | Desain/modifikasi/penambahan mesin | Task | Engineering | Engineering + Production | Belum Mulai | 0% | 18 Feb 2027 | Sesuai jadwal |
| MOP-06 | Instalasi & trial | Task | Engineering | Engineering + Production | Belum Mulai | 0% | 19 Mar 2027 | Sesuai jadwal |
| MOP-19 | Perizinan & tender renovasi | Task | Engineering | COO + Production | Belum Mulai | 0% | 7 Apr 2027 | Sesuai jadwal |
| MOP-06 | MC Development & Balancing | Project | Engineering | Yusuf Hamdani | Berjalan | 5% | 16 Apr 2027 | Sesuai jadwal |
| MOP-06 | Standardisasi & ukur efisiensi | Task | Engineering | Engineering + Production | Belum Mulai | 0% | 16 Apr 2027 | Sesuai jadwal |
| MOP-19 | Renovasi fisik | Task | Engineering | COO + Production | Belum Mulai | 0% | 23 Agu 2027 | Sesuai jadwal |
| MOP-19 | Relokasi mesin & peralatan dari Cipondoh | Task | Engineering | COO + Production | Belum Mulai | 0% | 23 Sep 2027 | Sesuai jadwal |
| MOP-19 | Sangiang (Layout, LT, Renov, Move) | Project | Engineering | Tarwipin | Berjalan | 7% | 27 Sep 2027 | Sesuai jadwal |
| MOP-19 | Commissioning & trial produksi | Task | Engineering | COO + Production | Belum Mulai | 0% | 27 Sep 2027 | Sesuai jadwal |
| MOP-12 | Compliance (CPPOB, HACCP, ISO) | Project | QAQC | — | Berjalan | 24% | 31 Des 2027 | Sesuai jadwal |
| MOP-12 | Pre-assessment / audit eksternal | Task | QAQC | COO + QAQC | Belum Mulai | 0% | 31 Des 2027 | Sesuai jadwal |
| MOP-12 | Sertifikasi | Task | QAQC | COO + QAQC | Belum Mulai | 0% | 31 Des 2027 | Sesuai jadwal |
| MOP-05 | Kurasi Pareto C by Manuf | Project | PPIC | Yayat | Berjalan | 93% | – | Belum ada target |
| MOP-08 | Automate ERP B2B – COGM | Project | Operations (COO) | Ali | Belum Mulai | 0% | – | Belum ada target |
| MOP-17 | Optimizing WH Occupancy & Racking | Project | Warehouse & Logistics | — | Belum Mulai | 0% | – | Belum ada target |
| MOP-18 | Ramadhan Strategy | Project | Operations (COO) | — | Belum Mulai | 0% | – | Belum ada target |
| MOP-22 | Efisiensi Gas | Project | Production | Yusuf Hamdani / Fajar | Belum Mulai | 0% | – | Belum ada target |
| MOP-23 | AHU Ruang Produksi | Project | Production | Agung / Yusuf Hamdani | Belum Mulai | 0% | – | Belum ada target |
| MOP-24 | Coding Machine | Project | Production | Dewa / Yusuf Hamdani | Belum Mulai | 0% | – | Belum ada target |
| MOP-25 | Machine Guidance & Part Management | Project | Engineering | Yusuf Hamdani / Heri | Belum Mulai | 0% | – | Belum ada target |
| MOP-26 | Reject Kemasan/Packaging | Project | QAQC | Shafry / Rama | Belum Mulai | 0% | – | Belum ada target |
| MOP-27 | Water Heater untuk Cleaning | Project | Production | Yusuf Hamdani / Ardiansah Setiawan | Belum Mulai | 0% | – | Belum ada target |
| MOP-28 | Baking Mate Evaluation | Project | QAQC | Shafry / Tri | Belum Mulai | 0% | – | Belum ada target |
| MOP-29 | Climate Chamber - Uji stability NPD | Project | R&D | Nia / Adi | Belum Mulai | 0% | – | Belum ada target |
| MOP-30 | Efisiensi Listrik | Project | Production | Dewa / Yusuf Hamdani | Belum Mulai | 0% | – | Belum ada target |
| MOP-31 | Optimalisasi Akurasi Pengiriman | Project | Fulfillment | Sofi / Randa | Belum Mulai | 0% | – | Belum ada target |
| MOP-32 | Optimalisasi Produktivitas Packing | Project | Fulfillment | Sofi / Randa | Belum Mulai | 0% | – | Belum ada target |
| MOP-33 | K3 - APAR | Project | Warehouse & Logistics | Sofi / Ardiansah Setiawan | Belum Mulai | 0% | – | Belum ada target |
| MOP-34 | Perbaikan Area Picking | Project | Fulfillment | Sofi | Belum Mulai | 0% | – | Belum ada target |
| MOP-35 | Evaluasi Penggunaan Oven | Project | Production | Tarwipin / Dewa | Belum Mulai | 0% | – | Belum ada target |
| MOP-36 | Kapasitas Meja Resting | Project | Production | Yusuf Hamdani / Dewa | Belum Mulai | 0% | – | Belum ada target |
| MOP-37 | Pengkodean Secara Batch | Project | Production | Bintang / Shafry | Belum Mulai | 0% | – | Belum ada target |
| MOP-38 | Perubahan Metode Packing #1 | Project | Fulfillment | Sofi / Eva | Belum Mulai | 0% | – | Belum ada target |
| MOP-39 | Pest Control & Hygiene Revamp | Project | QAQC | — | Belum Mulai | 0% | – | Belum ada target |
| MOP-40 | Facility & Working Env. Improvement | Project | Production | — | Belum Mulai | 0% | – | Belum ada target |
| MOP-41 | Traffic & Safety (K3) Marking | Project | Engineering | — | Belum Mulai | 0% | – | Belum ada target |
| MOP-42 | Time & Motion Study (SKU Repack) | Project | Production | — | Belum Mulai | 0% | – | Belum ada target |
| MOP-43 | Maintenance System Std. | Project | Engineering | — | Belum Mulai | 0% | – | Belum ada target |
| MOP-44 | Sensory Expert & Lexicon Dev | Project | R&D | — | Belum Mulai | 0% | – | Belum ada target |